The chemical feeding rate vary, but are usually within
1-3 ppm for continuous treatment and 5 - 10 ppm for
shock treatment. Generally the shock dosing system is
designed at 5-8 mg/liter of Cl2. As soon
as a trace of free chlorine HOCl appears at the cooling
tower return line, the shock dosing is stopped. The
reason is if it is a wooden tower with wooden slats,
HOCl above 1 mg/liter will start to attack the cellulose
fibers of the wood and can greatly reduce its physical
strength, to the point of collapse. So that's why it
is a good practice to shut off the chlorinator when
cooling tower return shows an HOCl residual of about
0.5 mg/liter.
Now if the tower is plastic
or other material, then the 0.5 mg/liter is not so critical,
however, it has been shown over the years that the 0.5
mg/liter residual at the tower return is a good indication
that you have the biofouling under control.
There are no hard and fast
rules for cooling water biofouling control. Each application
has its own peculiarities depending on;
- geographical location
- if it is a recirculation
system
- if it is a once through
system
- if it is fresh water
- if it is seawater
The Cl2 dosage
is based on the max. pumping rate of the cooling water
pumps at 5 mg/liter for shock dosing. With once through
systems, you also have marine growths like clams, etc.
to be concerned about. However, with recirculating systems
and functions to consider as follows:
- Other chemicals corrosion
inhibitors can cause problems when using an analyzer.
Typically the analyzer cell will be plated by the
inhibitor which may reduce the cell output, if the
level of inhibitor is constant than it can be allowed
for which the normal levels of inhibitor found in
cooling towers about 10-15 mg/liter.
- Number of times the water
recirculates. Shock dosing duration and interval is
dependent on the season in relation to the level of
algae, etc. in the water. In other words, generally
in European climates for example you only shock in
the summer - no need in the winter. In tropical climates,
you may have to shock dose all year with low level
continuous chlorination. It depends on geographical
location.
- Generally make-up water
does not create a problem as we are only concerned
about controlling algae, etc.
- Temperature of water in
the basin is not generally a concern as we don't normally
chlorinate the basin water. The chlorine solution
is normally added at the recirculating pump intakes.
- For the system circulation
time of cooling water (duration time), you set up
the system to supply a shock dose of 5 mg/liter for
as long as it takes the water to reach the cooling
tower return, which is generally about 20 - 30 minutes.
So, if recirculation time
is 40 minutes say, then you shock dose at 5 mg/liter
for 40 minutes and shut-off the system. Now you measure
the HOCl residual when it falls off to zero, maybe 6-8
hours, the interval time, you start the shock dosing
cycle again. So, you set the duration time to 40 minutes
and the interval timer to say 8 hours. Then every 8
hours, the system will shock for 40 minutes and stop.....
8 hours later it will repeat.
There are three variables
you can adjust to give the optimum performance for biofouling
control:
- Actual chlorine feed rate
- Duration of the shock
- Interval between shocks
Remember that the biofouling
control is an art, not a science !!!
1) Type of Chlorination
As previously discussed,
there are two methods of chlorination used in the treatment
of cooling water. They are as follow:
A choice of continuous or
shock treatment must be made with consideration to results
desired, chlorine consumed and water to be treated.
Shock treatment is usually the choice in the cooling
water recirculation system of cooling tower.
- Continuous Chlorination:
This provides a constant feed of chlorine for 24 hours
a day and at a low dosage, generally in the range
of 1 to 3 parts per million (ppm = mg/l).
- Shock Chlorination: This
provides a periodic chlorination generally at dosage
of 5 - 10 ppm. The length of the treatment period
and frequency of the treatment is usually adjusted
to meet the requirements of each application. A sufficient
chlorination should be provided during each treatment
cycle. The length of treatment should be no less than
the time interval for water to pass through the system.
The frequency will vary with ambient and water temperature,
location and demand. Sometimes it is necessary to
chlorinate continuously at a low level - say 0.5 to
1 ppm dose to maintain the system clean between shock
doses but this procedure is generally confined to
tropical where there is a continuous presence of biofouling
matter. In Korea, a common practice is to shock dose
in the summer as biofouling does not become a problem
in the winter. Generally three chlorination periods
per day are used.
Control of Duration time in The Shock Treatment: The
duration is generally set to match the cooling water
recirculation time and seasonal conditions. Capital's
Shock Chlorination System is using a dual timer.
One timer (t1), 0 - 60 minutes, is used to control
the time. The chlorinator is producing chlorine solution
by opening and closing the vacuum valve adjustable
0 - 60 minutes. The ejector has water running through
it continuously; it is the opening of vacuum valve
which allows chlorine gas under vacuum into the ejector
and the closing of the vacuum which stops the flow
of chlorine to the ejector.
The other timer (t2), 0 - 24 hours, is used to control
how often the 0 - 60 minute timer (t1) operates. For
instance, t1 could be set at 30 minutes, t2 could
be set at six hours then automatically every six hours
the chlorinator will feed chlorine gas for 30 minutes,
then stop, then six hours later it will repeat.
The system is fully automatic operation, once the
optimum duration (t1) time and frequency (t2) time
has been decided at site. The duration, frequency,
and kg/hr of chlorine used must be set at site to
meet the site conditions, this will vary from site
to site according to geographical location and type
of cooling water application.
The timers we use can have its range changed on site
by adjusting electrical jumpers within the timer;
t1 and t2 is the same timer with jumpers set to 0
- 60 minutes and 0 - 24 hours. The motorized or solenoid
valve located in the gas vacuum line is controlled
by a three position selector switch (ON - OFF - AUTO).
When the switch is in the "ON" position,
the solenoid will remain open and feed chlorine gas
to the ejector. When the switch is in the "OFF"
position, the solenoid will remain off (no chlorine
feed). When the switch is in the "AUTO"
position, the solenoid valve will cycle on and off
according to the settings on the "Frequency"
and "Duration" timers mounted on the local
control panel.
2) Design Factors for Feeding
Rate of Chlorine
Chlorination equipment should
be sized to provide a chlorine dosage several times
that the final TRC [Total Residual Chlorine = Free Residual
Chlorine (FRC) + Combined Residual Chlorine (CRC)] level
allowed. This provides chlorinator capacity to meet
the demand in the system, and losses of chlorine through
aeration in the cooling towers. Feed equipment should
be sized for the minimum anticipated feed rate, using
the below equations:
Pound/day of chlorine = [Recirculation
Rate of Cooling Water (GPM)] x [Rate of Dosage (ppm)]
x 0.012 or
Kilogram/hr of chlorine =
[Recirculation Rate of Cooling Water (CMH)] x [Rate
of Dosage (ppm)] x 0.001
The chlorine consumption
per day of 10,000 m3/hr cooling water and
6 ppm dosage at three cycles per day and 30 minutes
duration per each is:
10,000 m3/hr x
6 ppm x 0.001 = 60 kg/hr of chlorine
60 kg/hr x 30/60 hr x 3 cycles = 90 kg/day of chlorine
3) Design Factors for Chlorine
System
Four major factors must be
given consideration in the chlorination system. They
are:
- Cooling Water Recirculation
Flow Rates
- Chlorine Demand
- Nature of the interferences
- System Retention Time
4) Typical Gas Chlorination
Dosage Rate
The typical rates in PPM
or mg/l are for average Conditions. For special applications,
consult with Capital Controls or Chungrok ENC Company.
Chlorination Treatment
For Typical Dosage Rates in PPM or mg/l |
Algae |
3-5 |
Bacteria |
3-5 |
BOD
Reduction |
10 |
Color
(Removal) |
Dosage
depends on type and extent of color removal desired.
May vary from 1 to 500 |
Cyanide
Reduction to Cyanate
Complete Destruction |
2.7
times cyanide content
7.3 times cyanide content |
Hydrogen
Sulfide Taste and Odor Control
Destruction |
2
times hydrogen sulfide content
8.4 times hydrogen sulfide content |
Iron
Bacteria |
1-10
varying with amount of bacteria to control |
Iron
Precipitation |
0.64
times iron content |
Manganese
Precipitation |
1.3
times manganese content |
Odor |
1-3 |
Sewage
Raw Sewage
Trickling Filter Effluent
Activated Sludge Effluent
Sand Filter Effluent |
15-20
Average dosage 3-8
Average dosage 3-8
Average dosage 3-8 |
Slime |
3-5 |
Swimming
Pool |
1-5 |
Taste |
1-3 |
Water
Cooling
Chilling
Washdown
Well
Surface |
3-5
20
50
1-5
1-10 (There are many variables that can effect
surface water and treatment required. |
*
The rates in ppm. or mg/l given are for average
conditions. Consult for special applications. |
5) Chlorine Gas Feeder Sizing
Parameters
There are several design
parameters that will enable a gas feeder to be
sized properly. These parameters are:
(1) Flow Rate
The flow of water to be treated
is a primary concern for proper system design. Flow
rate data based on the recirculating cooling water should
be obtained for the following conditions:
- Flow Rate: Constant _______
Variable ________
- Initial Plant Operation ________ GPD ________ (m3/h)
- Average Daily ________ GPD _________ (m3/h)
- Peak Daily ________ GPD _________ (m3/h)
- Future Design Requirement __________ GPD __________
(m3/h)
(2) Chlorine Demand
Accurate demand data is vital
to sizing a gas feed system. A chlorine demand
profile of the water being treated should always be
included in the standard water quality analysis
completed prior to plant design.
The impurities responsible
for this demand include compounds containing iron, manganese,
nitrates and sulfides. When chlorine is added to water,
the amount reacting depends on the amount and type of
impurities, pH, the amount of contact time, the temperature,
and the amount of chlorine applied. The difference between
the amount of chlorine applied (chlorine dosage) and
the amount of chlorine residual remaining after the
reaction is complete is known as the "chlorine
demand" of the water.
CHLORINE DEMAND = CHLORINE
DOSAGE - CHLORINE RESIDUAL
When the chlorine demand
of a water is considered, it is always necessary to
know pH, the conditions under which the data was obtained,
and the temperature of the water, since the free chlorine
(hypochlorous acid, HOCl) depends on pH and temperature
of water.
As with flow rate data, chlorine
demand data should be obtained for the following conditions:
- Chemical Demand: Constant
_______ Variable ______
- Initial Plant Conditions ______ ppm (mg/l)
- Average Conditions _______ ppm (mg/l)
- Peak Conditions _______ ppm (mg/l)
- Future Design Requirements ______ ppm (mg/l)
(3) Feed Rate Required
Proper feeder sizing is a
most critical requirement for proper system operation.
The gas feed rate should be calculated for each plant
condition, i.e. initial, average, peak, etc. The system
should be sized for maximum dosage and flow requirement.
Since most gas feed equipment is easily down-sized in
the field, feed rate capacity conversion parts should
be specified to prevent system over sizing during normal
operation.
System over-sizing is the
most common design error resulting in poor system performance.
Because process and treatment facilities are designed
for future as well as existing conditions, it is not
uncommon to find that a gas feeder sized for maximum
design feed rates is grossly over-sized for initial
conditions. By using capacity feed rate conversion parts,
the proper capacity equipment for initial conditions
can be installed, then as flow rates increase, the feed
rate capacity can be increased as necessary up to the
design maximum.
|